Sanya jinjialing community three-dimensional parking garage for use at the end of the year

Issuing time:2017-10-16 16:33

On August 21, as the last building was capped, jinjialing community parking space project entered the construction, plaster, indoor and outdoor decoration phase.

In four months, three independent parking buildings will be officially put into use. At that time, 260 parking Spaces will relieve the parking problems of jinjialing community and surrounding residents. It will play a positive role in improving the traffic environment of the area, beautifying the city's appearance and improving the urban infrastructure.

260 parking Spaces alleviate parking problems for community residents

In recent years, with the rapid economic development, the residential buildings, shops, hotels and other buildings in the community of jinjialing have sprung up, which has attracted a large number of residents to rent apartments.

The rapidly expanding population and limited land resources have further intensified the shortage of infrastructure. Among them, "parking difficulty" is particularly obvious.

"Using limited space to plan some parking Spaces is just a drop in the bucket. Jin jialing community officials said. At the end of 2016, jinjialing community three-dimensional parking space project came into play and began to clean up the surface... It's a moment that residents of the golden chicken-ling community have been hoping for.

"Construction of the three independent parking building, with a total construction area of 7820 square meters, construction area of 2705 square meters, the 1 # floor 2 # building construction area of 1723 square meters, 3 # building construction area of 3392 square meters (including the basement area: 526 square meters)." Sun rongmeng, the head of the project site of the sanya city housing authority project, said that 1# and 3# parking buildings are 6 stories on the ground, and the building height is 16.75 meters. 2. The parking garage is 7 floors above ground, and the building height is 19.4 meters. A floor of the parking garage is a fire pump room and sink.

"When the parking garage is built, 260 parking Spaces will be provided for the golden chicken community and surrounding areas." "Said sun.

The sanya daily reporter saw at the project site, three three-dimensional parking buildings next to jinjialing community east sixth lane and east eighth lane intersection, along the east sixth lane one line. At present, the three buildings have been completed with the main sealing of concrete and water, fire, steel structure and equipment. The next step is to complete construction, plaster, indoor and outdoor decoration, steel structure installation, fire fighting installation, intelligent parking equipment installation, etc.

"It is expected to be completed and put into use at the end of December." "Sun said happily.

Solve the three problems and advance the project construction

"It is expected to be operational by the end of this year."

Before the start, sun rongmeng and liu ruixing, the site head of project construction, were confident.

However, on the first day of the first day of cleaning, I received a noise complaint from the 12345 municipal service hotline. This "understudy" has made them realize that project progress may not be so smooth.

It is not surprising that the complex pipeline environment has made it more difficult to clean the surface. It involves the transfer of transformers, high voltage cables, fire pipelines, water supply pipelines, communication cables and other pipelines to consider the safety of construction and the daily life of residents.

With the efforts of sun rongmeng's coordination and related units, the relocation work was completed on March 15, 2017, and the project was officially started on March 24.

Who knows, the first day of the project received another noise complaint. "The site is close to the residential building and any construction will affect the rest of the residents." "Mr. Sun said.

What happens when you face this problem again?

Sun chose a positive attitude and decided to adjust the construction arrangement after communicating with the construction side, so as to accelerate the construction speed on the basis of reducing the impact on the residents.

"The construction time will be adjusted from 7:30am to 11pm, from 1430pm to 20pm, away from the rest of the residents and increase the construction staff." "Mr. Sun said.

The problem of noise is solved, and new problems ensue.

First, the construction site is narrow, there are no construction materials, no processing materials; Second, when pouring concrete, other buildings need to be shut down to facilitate the access of cement tankers; Three is unable to set the tower crane, causing some materials to need to carry on secondary human transport. "These three problems, in the end, are limited space." "Mr. Sun said.

In order to solve the problem of the site, the construction company took the water construction method, from the 1# building gradually to the inside. "From 1# 1 building, 1# building cement, 2# building steel bar, 3# building to install the template." At the same time, some materials are processed in other places, liu said.

"In the early stage, there were more ups and downs, and we had to catch up on the progress. We were worried about the complaint and the site was small. Fortunately, everything went according to plan, and the full cap was capped on August 21, 10 days earlier than planned for August 31." "Mr. Sun said.


Company email: shaanxirunze@163.com
contact address: xi 'an of shaanxi province by the open area not ended road 123 Eurasian building, room 12303, building 1 unit 3
Contact us: 029-86684420
18092504760
website qrcode

Scan to check the